PM Quiz June 2020

Compiled by Himadri Sekhar Chowdhury

Questions:

  1. What does work performance data analysis provide?
  2. What is the 100 percent rule in WBS?
  3. Why should you document discretionary dependencies?
  4. What do you get when you do a summation of the control accounts?
  5. What is a team charter?

Answers:

  1. Completion status of deliverables and other relevant project performance data
  2. Total of work at the lowest levels should roll up to the higher levels so that nothing is left out
  3. As they can create arbitrary total float values and can limit later scheduling options
  4. The cost baseline
  5. Guidance on how the team will make decisions, conduct meetings, and resolve conflict