PM Quiz November 2020

Compiled by Himadri Sekhar Chowdhury

Questions:

  1. What are the three baselines in a Project Management Plan?
  2. What is the 100 percent rule in WBS?
  3. What is attribute sampling in Control Quality?
  4. What is the downside of keeping too much inventory?
  5. What is push communication?

 

Answers:

  1. Scope, Schedule and Cost
  2. Total of work at the lowest levels should roll up to the higher levels so that nothing is left out or no extra work performed
  3. The result either conforms or does not conform
  4. It may result in high operations cost and reduce the organization’s profit
  5. Sent or distributed directly to specific recipients who need to receive the information