PM Quiz

Compiled by Somashekar N T

Questions:

  1. What is the type of knowledge that includes personal knowledge and can be difficult to articulate and share such as beliefs, experience, and insights?
  2. What is the agreement by everyone in the group on a single course of action?
  3. What is the method called for obtaining early feedback on requirements by providing a working model of the expected product before actually building it?
  4. What is the relationship in which a schedule activity has more than one predecessor?
  5. What is a significant point or event in a project, program or portfolio?

 

Answers:

  1. Tacit Knowledge
  2. Unanimity
  3. Prototype
  4. Path Convergence
  5. Milestone